The road was partially opened on 9 December 2003 for traffic entering from local junctions, then fully opened on 14 December 2003 The historical investment structure of the project differs greatly from the present position. The original concession was held by a consortium of Trafalgar House (Kvaerner) and Italstat (Autostrade). The Kvaerner share passed to Macquarie when Kvaerner was restructured in 1999. Macquarie then bought out the Autostrade share when the project was refinanced in 2006
List of the country updates

Country updates

  • December 12, 2003

    John Laing, together with its partner Sodexho, was appointed preferred bidder to build the project

  • August 31, 2003

    The Private Finance Initiative (PFI) contract between the city council and Aurora Sunderland Streetlighting Ltd will see old and worn equipment replaced

  • February 09, 2000

    The road opened to traffic

  • October 01, 1996

    The contract was signed

  • July 24, 1996

    The contract was awarded to Connect A30/A35 Limited, a consortium of companies comprising BICC plc, Philipp Holzmann AG and WS Atkins