The consortium led by ACS and FCC has claimed US$260 million to the Peruvian government due to the land where the project is being developed do not presents the conditions agreed in the contract

Subscribe to our newsletter and get the latest news and business opportunities in your inbox
The consortium led by ACS and FCC has claimed US$260 million to the Peruvian government due to the land where the project is being developed do not presents the conditions agreed in the contract. This has caused more than one year delay in the construction process.