Infrastructure Ontario (IO) and the Ministry of Transportation (MTO) have released a Request for Proposals (RFP) for the QEW Garden City Skyway – Bridge Twinning project in the Regional Municipality of Niagara, Canada.
The project includes constructing a new 2.2-km twin bridge to the north of the existing bridge, connecting St. Catharines and Niagara-on-the-Lake. The following Five teams have been pre-qualified and invited to bid on the project, which is being delivered using a Progressive Design-Build.
AtkinsRealisMajor Projects Inc.
- Applicant Lead: AtkinsRealis Major Projects Inc.
- Design Team: AtkinsRealis Canada Inc., Hatch Ltd.
- Construction Team: AtkinsRealis Major Projects Inc.
Garden City Connectors
- Applicant Lead: Aecon Infrastructure Management Inc., Sacyr Canada Inc. (DBJV)
- Design Team: Parsons Corporation
- Construction Team: Aecon Infrastructure Management Inc., Sacyr Canada Inc.
Garden City Link
- Applicant Lead: Acciona Infrastructure Canada, Inc., Amico Major Projects Inc., Pomerleau, Inc. (Integrated JV)
- Design Team: WSP Canada Inc.
- Construction Team: Acciona Infrastructure Canada, Inc., Amico Major Projects Inc., Pomerleau, Inc.
Peter Kiewit Sons ULC
- Applicant Lead: Peter Kiewit Sons ULC
- Design Team: Kiewit Engineering Group Canada ULC
- Construction Team: Peter Kiewit Sons ULC
Skyway Bridging Partners
- Applicant Lead: Dragados Canada Inc., Construction Demathieu & Bard Techno, Green Infrastructure Partners
- Design Team: Arcadis Professional Services (Canada) Inc., GHD Ltd., Pedelta
- Construction Team: Dragados Canada Inc., Construction Demathieu & Bard Techno, Green Infrastructure Partners