Purple Line Transit Partners gives a deadline to quit the Maryland LRT P3 in case of no deal

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Purple Line Transit Partners (PLTP), a joint venture of Meridiam, Star America and Fluor, has given termination deadline to the Maryland Department of Transportation (MDOT) both parties cannot reach a settlement with over extensive delays and cost overruns for the Purple Line Light Rail P3 Project in Maryland. The consortium announced a 60-day termination notice putting the deadline to resolve the current issues by August 23, 2020.

PLTP filed a notice of termination after the failure to reach an agreement with its contractor on the matter of delay related costs. PLTP cites the following issues that caused almost 1000 days delay and half a billion USD in added costs: delays in receiving environmental permits, right-of-way, and land. Negotiations between two parties over who is responsible for the delays and related costs is expected to continue until August 23.

Currently, 40% of the construction works are completed for the 16-mile long project. Abandoning the works will bring major inconvenience to the inhabitants due to ripped up roads, incomplete tunnel, and partially built rail bridges. 

List of the country updates

Country updates

  • June 29, 2020

    Technical consultant appointed for student housing and medical plaza in Texas

    The Texas A&M University System (TAMUS) in the USA has announced Hill International and Sage Project Consulting are selected to provide project management and inspection services on the const...

    Read more
  • June 29, 2020

    Largest social infra P3 in USA history completed

    The largest public-private partnership (P3) social infrastructure project in U.S. history was completed in less than four years. The 1.2-million-gross-square-foot Merced campus expansion, known as UC...

    Read more
  • June 25, 2020

    Amazon launches US$2bn Climate Pledge Fund

    Amazon has launched The Climate Pledge Fund to support the development of sustainable technologies and services that will enable Amazon and other companies to meet The Climate Pledge—a commitmen...

    Read more
  • June 23, 2020

    MBTA approves contract amendment for the automated fare collection system PPP

    Massachusetts Bay Transportation Authority (MBTA) in the USA has approved a contract amendment delivered by John Laing Group for the state-of-the-art plan in improvements to fare collection and t...

    Read more
  • June 23, 2020

    Bidders selected for Gray 30th Street Station Redevelopment project

    Amtrak in the USA has selected a consortium of Plenary Infrastructure Philadelphia (PIP), Gilbane Building Company, Johnson Controls Inc., and Vantage Airport Group Ltd. to form a master developm...

    Read more

Share this update