Progress on construction work of Coronel Oviedo Hospital PPP project in Caaguazú

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

The Ministry of Public Works and Communications (MOPC) has announced that 40% of construction work has been completed for the Great Hospital of Coronel Oviedo in Caaguazu, Paraguay. 

The tasks carried out by the responsible consortium Jiménez Gaona and Lima SA Consortium - Itasa - Proel Ingeniería MMSA are:

  • reinforced concrete structures, placement of insulation, plastering, placement of subfloors, floors and masonry;
  • metal carpentry works, such as sheet metal frames, perimeter fencing, trapezoidal fabric, placement of hydraulic installations, sewer and storm drainage installations, electrical installation, and fire prevention systems; and
  • the effluent treatment plant, on the oxygen generating plant and treatment of bio infectious waste, as well as on weak signals, videos and the heliport.

MOPC awarded this work -via Resolution No. 185/2021 for an amount of PYG 151,247,999,999 (US$ 20.41 million).

 