The Peruvian Private Investment Promotion Agency (ProInversión), through its Committee on hydrocarbons and Energy Projects Pro Connectivity, has announced it has launched tender process re...
Read moreThe consortium led by ACS and FCC has claimed US$260 million from the Peruvian government due to the land where the project is being developed not meeting the conditions agreed in the contract. This has delayed construction works by more than one year
The consortium led by ACS and FCC has claimed US$260 million to the Peruvian government due to the land where the project is being developed do not presents the conditions agreed in the contract. This has caused more than one year delay in the construction process.