Construction works progresses for Heroes del Chaco bridge PPP project

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

The Ministry of Public Works and Communications in Paraguay has announced that the placement of beams in the access viaducts of the Héroes del Chaco Bridge is in the final stage.

The placement of the last beams on the left bank (Costanera Norte) are planned to be completed this week, which will join the viaduct with the avenue connecting the bridge with the Botanical Road Corridor.

The Héroes del Chaco Bridge is a 600 m cable-stayed bridge that is being built over the Paraguay river connecting Asunción and Chaco’i. The bridge will have two access viaducts, the section on the right bank (Chaco'i) is 1,500 m long whereas the section on the left bank (Costanera Norte) measures 300 meters. The scope of the project also includes a 7 km road connecting the Costanera Norte de Asunción to the roundabout on the route between Falcón and Remanso. 

The Union Consortium, comprising CDD Construcciones and Constructora Heisecke, is in charge of the project.

List of the country updates

Country updates

  • August 04, 2022

    Construction work progresses for multimillion Highway PPP project in Paraguay

    The Ministry of Public Works and Communications has announced that 93.58% of construction work has been completed for Ñumí - San Juan Nepomuceno highway PPP project in Caa...

    Read more
  • August 02, 2022

    Reconversion works started for Port of Asunción project

    The Ministry of Public Works and Communications (MOPC) has started the reconversion works for the Port of Asunción in Paraguay. The project involves the restoration of the port build...

    Read more
  • August 02, 2022

    Tender launched for inspection of the works of the third stage of the Bioceanic route

    The Ministry of Public Works and Communications (MOPC) in Paraguay has launched a tender seeking consulting companies for inspection of the works of the third stage of the Bioceanic route, P...

    Read more
  • July 29, 2022

    Access Viaduct structure completed for Heroes del Chaco bridge PPP project

    The Ministry of Public Works and Communications (MOPC) has announced the completion of structural works for the access viaduct of the Heroes del Chaco bridge. With these milestones, the consortium of...

    Read more
  • July 29, 2022

    CAF seeks technical adviser for sanitation project in Paraguay

    Development Bank of Latin America (CAF), on behalf of the Government of Paraguay, has issued a request for proposal (RFP) for feasibility studies and detailed designs of the sewer systems, wastewater...

    Read more

Share this update