73% of construction complete for Bella Vista water treatment plant PPP project in Bañado Norte

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

The Ministry of Public works and Communications in Paraguay has announced that Bella Vista Wastewater Treatment Plant (WWTP) has reached 73.2% completion. The construction works for buildings housing pumping station, ​​thick bars in the wastewater processing sector, sewage effluents, and the electrical power substation are now underway. 

Developed on an area of ​8,100 square meters in Bañado Norte, the plant will have initial capacity to process 2 cubic meters of wastewater per second, which will be increased to 4.4 cubic meters per second during second phase of the project. Acciona is responsible for the project development. The estimated investment value for the project is PYG10.5 billion (US$15.03 million).

The WWTP is part of three newly built plants included in the sanitation program for the Asunción Bay. It will benefit 1,200,000 people residing in the capital's neighborhoods, Fernando de la Mora, and Luque.

List of the country updates

Country updates

  • April 07, 2022

    Construction works begin for Bioceánica bridge PPP Project

    The Ministry of Public Works and Communications (MOPC) of Paraguay has announced that the construction of the Bioceánica bridge has begun. The 1,300 meter-long Bioceánica brid...

    Read more
  • April 07, 2022

    Tender to be launched soon for Cuatro Mojones- Quiindy PY01 road project in Paraguay

    The Ministry of Public Works and Communications (MOPC) in Paraguay has announced that it is planning to launch tender notice for the PY01 national route section connecting Cuatro Mojones to Quiindy....

    Read more
  • April 06, 2022

    Paraguay awards Monday Bridge PPP project in Eastern Metropolitan Corridor

    The Ministry of Public Works in Paraguay has awarded the concession contract for the Monday bridge to the consortium of Constructora Heisecke SA and Construpar SA. The 4.6 km long bridge will be bui...

    Read more
  • March 23, 2022

    Details emerged for Wastewater Treatment Plant PPP project in Caacupé

    The government of the department of Cordillera and Sustainable Development of the Chamber of Senators Paraguay has issued the details related to the Wastewater Treatment Plant PPP project in...

    Read more
  • March 11, 2022

    Progress in construction for Route PY07 Superhighway Junction PPP project in Puerto Indio

    The asphalt paving of the access to the Torocuá port, located in the district of Ñacunday, department of Alto Paraná, is progressing at a full pace in Paraguay.  Puerto Toro...

    Read more

Share this update