64% construction works finished for PY09 Transchaco route PPP project

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

The Ministry of Public Works and Communications in Paraguay has shared that approximately 64% of construction work has been finished for the PY09 Transchaco route concession. The route is 553 km long with four sections.

The concession is divided into a total of 8 lots containing 4 sections. The project is being financed by the Inter-American Development Bank (IDB) and the Development Bank of Latin America (CAF). The work progress for each lot is as follows:

  • Lot 1 (km 50 to km 112): Undertaken by Constructora Heisecke SA, 45% completed;
  • Lot 2 (km 112 to km 173):  Undertaken by Transchaco Route 9 Consortium, 54.44% completed;
  • Lot 3 (km 173 to km 250):  Undertaken by Avanza Chaco Consortium, 30% completed;
  • Lot 4 (km 250 to km 326):  Undertaken by Tocsa SA, 21.16% completed;
  • Lot 5 (Km 326 to km 390):  Undertaken by Concretmix SA, 112% completed;
  • Lot 6 (km 390 to km 450):  Undertaken by Boquerón Consortium, 110% completed;
  • Lot 7 (km 450 to km 525):  Undertaken by Constructora Asunción SA y Asociados Consortium, 52% completed;
  • Lot 8 (km 525 to km 603):  Undertaken by Rovella Carranza SA, 90% completed;

The construction duration for the concession is 2 years with 4 years of the maintenance period.

 