64% construction works finished for PY09 Transchaco route PPP project

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

The Ministry of Public Works and Communications in Paraguay has shared that approximately 64% of construction work has been finished for the PY09 Transchaco route concession. The route is 553 km long with four sections.

The concession is divided into a total of 8 lots containing 4 sections. The project is being financed by the Inter-American Development Bank (IDB) and the Development Bank of Latin America (CAF). The work progress for each lot is as follows:

  • Lot 1 (km 50 to km 112): Undertaken by Constructora Heisecke SA, 45% completed;
  • Lot 2 (km 112 to km 173):  Undertaken by Transchaco Route 9 Consortium, 54.44% completed;
  • Lot 3 (km 173 to km 250):  Undertaken by Avanza Chaco Consortium, 30% completed;
  • Lot 4 (km 250 to km 326):  Undertaken by Tocsa SA, 21.16% completed;
  • Lot 5 (Km 326 to km 390):  Undertaken by Concretmix SA, 112% completed;
  • Lot 6 (km 390 to km 450):  Undertaken by Boquerón Consortium, 110% completed;
  • Lot 7 (km 450 to km 525):  Undertaken by Constructora Asunción SA y Asociados Consortium, 52% completed;
  • Lot 8 (km 525 to km 603):  Undertaken by Rovella Carranza SA, 90% completed;

The construction duration for the concession is 2 years with 4 years of the maintenance period.

 

List of the country updates

Country updates

  • April 29, 2022

    Paraguay receives 19 bids for Route PY07 Superhighway Junction PPP project in Puerto Indio

    Ministry of Public Works and Communications (MOPC) in Paraguay has received 19 offers from companies and consortiums interested in carrying out the paving and maintenance works of a 60 km section of r...

    Read more
  • April 29, 2022

    Construction works underway for Yberá de San Lorenzo bridge PPP project in San Lorenzo

    Ministry of public works and communications in Paraguay has announced starting of repair works for the Yberá de San Lorenzo bridge, which provides connection over the San Lorenzo stream. The au...

    Read more
  • April 29, 2022

    Operations to begin soon for Ruta Bella Vista Norte – Puentesiño PPP project

    Ministry of Public Works and Communications in Paraguay has announced that the asphalt paving works for the Ruta Bella Vista Norte to Puentesino stretch are in final stage. The authority expects to be...

    Read more
  • April 25, 2022

    73% of construction complete for Bella Vista water treatment plant PPP project in Bañado Norte

    The Ministry of Public works and Communications in Paraguay has announced that Bella Vista Wastewater Treatment Plant (WWTP) has reached 73.2% completion. The construction works for buildings housing...

    Read more
  • April 07, 2022

    Tender to be launched soon for Cuatro Mojones- Quiindy PY01 road project in Paraguay

    The Ministry of Public Works and Communications (MOPC) in Paraguay has announced that it is planning to launch tender notice for the PY01 national route section connecting Cuatro Mojones to Quiindy....

    Read more

Share this update