47.5% construction work completed of Chacao Bridge

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

The Ministry of Public Works has presented the progress of the construction of the Chacao Bridge which will connect the island territory with the mainland through a high-standard road that will allow a 2.7 km journey in just a few minutes.

According to the new work program:

  • construction work will be 50% complete by the end of this year (currently at 47.5%);
  • construction of the southern pier should be completed in Q1 of 2025;
  • construction of the northern pier should be completed in H2 of 2025; and
  • the central pier should be ready by mid-2026, to complete the work in H2 of 2028.