Colombia's National Infrastructure Agency (ANI) has received two bids for the Santa Ana - Mocoa - Neiva motorway PPP project.
The two teams that have bid for the project are the following:
The project is scheduled to be awarded on 9 June 2015. Construction works are expected to take 4 years to be finished.
The project involves the development of 22 km of four-lane highway, 32 km of two-lane highway and the upgrade of a stretch of 422 km road. The project includes the development of 3 tunnels and 3.5 km of several bridges, among others.
The total project investment is estimated at P$1.5 billion (US$620.8 million).
The project is part of the second wave of concessions of the 4G highway plan. This second phase will involve a total of 9 projects and require US$14.2 billion.
The tender documents for the project were published in December 2015 together with three other road PPP projects: