Infrastructure Ontario (IO) and Metrolinx have awarded a fixed-price contract of CAD757.1 million (USD626.25 million) to Strabag to design, build and finance the tunnel for the Scarborough Subway Extension project.
The Strabag team includes:
The project underwent an open, fair and competitive procurement process overseen by a third-party fairness advisor. Strabag submitted the proposal, which delivers the best value for Ontario taxpayers. It is being delivered through IO’s Public-Private Partnership (P3) model.
The Scarborough Subway Extension Advance Tunnel scope of work includes:
Onsite mobilization and pre-construction work began this spring, with launch shaft construction beginning in June 2021. Major tunnel boring is expected to begin next year.