NHAI releases RFP for seven road projects

Subscribe to our newsletter and get the latest news and business opportunities in your inbox
NHAI releases RFP for seven road projects The National Highways Authority of India (NHAI) has released lists of prequalified bidders for seven road projects under the DBFOT model. Final bids for these public private partnership (PPP) projects have to be submitted on September 29th (the three first projects of the table below) and 30th (the four final projects of the table below). The submission of the final bids will be done in e-tendering mode. InfraPPP India understands that the RFQs are already available in the e-tendering system.
See the projects in the table below:
Name of the roadLength (km)StateModelBidders
2-Laning Jowai- Meghalaya/ Assam Border section (km 69.200 -.173.200) NH-44
104
Megha-laya
BOT (toll)
List  (29 bidders)
4-laning Hospet-Chitradurga  NH-13 (299+0 - 418+6)
119.6
Karna-taka
BOT (toll)
List (27 bidders)
Rehabilization of Cuttak-Angul NH-42 (km 00.0000 - 112.0000)
112
Orissa
BOT (toll)
List (27 bidders)
4-laning Raipur/Bilaspur section  (km 00.0 - 125.200) NH-200
125.2
Chattis-garh
BOT (toll)
List  (33 bidders)
6-Laning Agra-Etawa section of NH-2 from (km 199.660 -323.525)
124.1
Uttar Pradesh
BOT (toll)
List (33 bidders)
Rehabilization of 4-laning of MH_ KNT _Border-Sangareddy section km 348 ti jn 493 - NH-9
145
Karna-taka and Andra Pardesh
BOT (toll)
List (24 bidders)
6- Lanning Etawah-Chakeri (Kanpur) Section of NH-2 (km 323.475- 483.687)
160
Uttar Pradesh
BOT (toll)
List  (24 bidders)
Some of these RFQs were submitted in 2010.
Considering the foreign bidders and having in mind that there around 20-25 Indian contractors-developers that bid for every single project in India, it is interesting to highlight the following things:
  • The location of the first project (in the state of Meghalaya) in the table has made it not very attractive to foreign bidders
  • In the 6-Laning of Agra-Etawa section of NH-2 we can see a new player in the Indian market: Ascendi -the highway operator owned by the portuguese contractor Mota Engil- in a joint venture with a strong local player, Essar Infrastructure. We can also see Hochtief, the german contractor controlled by Spanish conglomerate ACS in a joint venture with SREI Infrastructure. A Russian joint venture formed by Transtoy and OJSC has also qualifed.
  • In the 4-laning of Hospet-Chitradurga we still can see the very succesful joint venture of Soma Tollways and the Spanish Isolux Corsan. In other qualifications Soma is bidding on its own and Isolux has joined forces with C&C Construction.
  • In the Rehabilization of the section Cuttak-Angul of NH-42, bidders were the same as for the 4-laning of Hospet-Chitradurga.
  • Bidders for 6- Lanning Etawah-Chakeri (Kanpur) Section of NH-2 were the same as for the Rehabilization of 4-laning of MH_ KNT _Border-Sangareddy.
Follow us:
- Linkedin group (+ 1,100 members)
PPP News on Twitter (more than 475 followers)
Facebook (very few likers yet, Like us on facebook!)
List of country news

Country news

  • September 09, 2011

    Private equity investment in infrastructure in India 2011

    . Read more
  • November 28, 2011

    16 teams prequalified for Bhaupur-Khurja section of Eastern Dedicated Freight Corridor

    The Dedicated Freight Corridor Corporation of India Limited (DFCCIL) has selected bidders for Design and Construction of approximately 343 Route Km Double Line Railway between Bhaupur - Khurja Section of Eastern Dedicated Freight Corridor split in three Slices on Design-Build Lump Sum basis. Read more
  • January 21, 2012

    News Round-up. PPP in India

    Dear readers, there have been a couple of PPP projets moving forward during this week in India: Read more
  • March 10, 2013

    Cabinet approves Four laning of Bhuban-Dubari-Chandikhole section of NH-200 in Orissa

    The Indian Cabinet Committee on Economic Affairs has approved the implementation of the development of four laning of Bhuban-Dubari-Chandikhole section of National Highway-200 in Orissa under the National Highways Development Project (NHDP) Phase III on Design, Build, Finance Operate and Transfer (DBFOT) basis in Build-Operate-Transfer (BOT) (Toll) mode of delivery. Read more
  • June 17, 2013

    Soma - Isolux to finish road PPP project after Supeme Court ruling

    A recent Supreme Court ruling has stated that the Panipat-Jalandhar national highway in India, involving an investment of Rs. 4,500cr (US$780 million), will be completed by its existing contractor Soma/Isolux Infrastructure instead of the National Highway Authority of India (NHAI) as had been directed by the Punjab and Haryana high Court earlier. Read more