National Highways Authority of India (NHAI) has released lists of prequalified bidders for
seven road projects under the DBFOT model. Final bids for these
public private partnership (PPP) projects have to be submitted on September 29th (the three first projects of the table below) and 30th (the four final projects of the table below). The submission of the final bids will be done in e-tendering mode.
InfraPPP India understands that the RFQs are already available in the e-tendering system.
See the projects in the table below:
Name of the road | Length (km) | State | Model | Bidders |
---|
2-Laning Jowai- Meghalaya/ Assam Border section (km 69.200 -.173.200) NH-44 | 104 | Megha-laya | BOT (toll) | |
4-laning Hospet-Chitradurga NH-13 (299+0 - 418+6) | 119.6 | Karna-taka | BOT (toll) | |
Rehabilization of Cuttak-Angul NH-42 (km 00.0000 - 112.0000) | 112 | Orissa | BOT (toll) | |
4-laning Raipur/Bilaspur section (km 00.0 - 125.200) NH-200 | 125.2 | Chattis-garh | BOT (toll) | |
6-Laning Agra-Etawa section of NH-2 from (km 199.660 -323.525) | 124.1 | Uttar Pradesh | BOT (toll) | |
Rehabilization of 4-laning of MH_ KNT _Border-Sangareddy section km 348 ti jn 493 - NH-9 | 145 | Karna-taka and Andra Pardesh | BOT (toll) | |
6- Lanning Etawah-Chakeri (Kanpur) Section of NH-2 (km 323.475- 483.687) | 160 | Uttar Pradesh | BOT (toll) | |
Some of these RFQs were submitted in 2010.
Considering the foreign bidders and having in mind that there around 20-25 Indian contractors-developers that bid for every single project in India, it is interesting to highlight the following things:
- The location of the first project (in the state of Meghalaya) in the table has made it not very attractive to foreign bidders
- In the 6-Laning of Agra-Etawa section of NH-2 we can see a new player in the Indian market: Ascendi -the highway operator owned by the portuguese contractor Mota Engil- in a joint venture with a strong local player, Essar Infrastructure. We can also see Hochtief, the german contractor controlled by Spanish conglomerate ACS in a joint venture with SREI Infrastructure. A Russian joint venture formed by Transtoy and OJSC has also qualifed.
- In the 4-laning of Hospet-Chitradurga we still can see the very succesful joint venture of Soma Tollways and the Spanish Isolux Corsan. In other qualifications Soma is bidding on its own and Isolux has joined forces with C&C Construction.
- In the Rehabilization of the section Cuttak-Angul of NH-42, bidders were the same as for the 4-laning of Hospet-Chitradurga.
- Bidders for 6- Lanning Etawah-Chakeri (Kanpur) Section of NH-2 were the same as for the Rehabilization of 4-laning of MH_ KNT _Border-Sangareddy.
-