This article is part of a daily series of MegaProjects articles. If you want to know more about PPP projects with a considerable size visit our MegaProjects section. You can receive them by email on a daily basis.
Ottawa City Council (Ontario, Canada) has approved moving ahead with the Stage 2 project to bring light rail transit (LRT) farther and faster to communities in the east, the west and the south.
The Stage 2 report approved by Council includes recommendations changing the scope of the light rail transit project, the procurement model and the specific activities the City will undertake to implement Stage 2.
An expansion of the scope of the Stage 2 LRT Project was approved, including construction of an additional Maintenance and Storage Facility in the Moodie Drive area, final alignment changes and the following extensions to train lines:
The budget for the Stage 2 LRT project remains CAD3 billion (US$2.3 billion), as approved in 2015. The new Moodie Extension is included within the original budget, while the Trim and Airport Extensions are conditional on receiving 100 per cent federal and provincial funding.
Several related infrastructure works, such as widening of Highway 417 between Highway 416 and Maitland Avenue, are being bundled with Stage 2. This will improve construction integration, reduce detours, save money and reduce impacts to the community. The Stage 2 project will generate more than 21,000 person-years of employment.
The City will continue to work with its existing partner, Rideau Transit Group, to ensure an integrated and consistent expanded rail system while maximizing the amount of work to be procured under new competitions.
The Stage 2 expansion of the O-Train network will be undertaken through two new procurements:
With this Council approval, the project can go to market later this winter. A final Council report will be brought forward in early 2018 outlining the results of the procurement process and related activities, leading to the final design and beginning of construction. The Stage 2 project is planned to proceed with staggered openings to allow for faster expansions to LRT service:
Infrastructure Ontario (IO) and the Centre for Addiction and Mental Health (CAMH) have awarded a fixed-price contract to Plenary Health CAMH to design, build, finance and maintain the CAMH Phase 1C redevelopment project.
Read moreInfrastructure Ontario (IO) and Metrolinx have issued a Request for Qualifications (RFQ) for interested parties to design, build and finance the Union Station Enhancement project.
Read moreHealth Minister Terry Lake was joined by Kamloops-South Thompson MLA Todd Stone and officials with Interior Health, the Thompson Regional Hospital District and the Royal Inland Hospital Foundation to announce that the new CAD417 million (US$318 million) patient care tower project at Royal Inland Hospital is moving forward.
Read moreInfrastructure Ontario (IO) and Metrolinx have issued a Request for Proposals (RFP) to three shortlisted teams to design, build, and finance the Highway 401 Rail Tunnel project. Work is required at the Highway 401/409 intersection to accommodate GO Transit expansion along the Kitchener Corridor under Metrolinx's Regional Express Rail (RER) program.
Read moreThe start of construction for the George Massey Tunnel replacement project is one step closer after the provincial government issued environmental assessment certificate.
Read more